Work on the room for the X-ray device – status March 2022

There is still some work to be done before the X-ray device from Ulm, which arrived at the hospital at the end of 2021, can put into operation.

First of all, the large windows had to be bricked up. Then, a floor had to be installed in the room. After that, a ceiling structure had to be created, on which the heavy X-ray equipment would be suspended. So that it can be moved later.
Next, cables for a proper power supply had to be laid.